Sand Aggregate IndustryComprehensive Service Provider| model | PSGD1614 |
| Max feed size | 113 mm |
| CSS Range | 13 - 25 mm |
| Capacity(by hour) | 253 - 336 t/h |
| Motor power | 250 kW |
| Dimensions | 3941×2954×3771 mm |
| Weight | 43870 Kg |
*Note: The processing capacity of the PSGD1614 cone crusher may vary with different materials and feeding sizes.

Basic configuration includes ZG1238 vibrating feeder PCZ1512 heavy hammer crusher 22YK2060 vibrating screen*2 sets DMCA pulse deduster*5 sets etc.

At that time, the output of the production line of about 1000 tons, in addition to mining equipment, the introduction of intelligent mine management system, to achieve environmental protection production line, intelligent operation management.

In this production line it is configured on the green mining policy that can discharge various materials regularly.
Specification: 5.5'FT
Model: PSGD - 1614
Cavity Type: Short - head Extra - Coarse
Large - end Diameter of Crushing Cone: 1676 mm
Discharge Opening Adjustment Range: 13 - 25 mm
Feed Size at Min. Discharge Opening: 133 mm
Max. Feed Size: 113 mm
Processing Capacity: 253 - 336 t/h
Main Motor Power: 250 kW
Machine Weight: 43870 kg
Overall Dimensions: 3941×2954×3771 mm
Appearance: Check the machine body for cracks and deformation before startup and after shutdown. Tighten loose connection bolts and record any damages.
Lubrication: Check the lubricating oil level and quality weekly. Replace the oil every 200 - 300 hours if it's dirty or of poor quality. Refill when the level is low.
Discharge Opening: Measure the discharge opening size daily to ensure it's within the specified range. Adjust it according to the manual if abnormal.
Crushing Cone: Inspect the wear of the crushing cone every 500 - 800 hours. Replace it if the wear exceeds the limit. Also, check its installation firmness.
Transmission Parts: Regularly check the belt tension and its aging and cracking. Adjust or replace the belt as needed. Check the wear of drive shafts and bearings and replenish grease every 100 - 150 hours.
Electrical System: Check the motor wiring for looseness, aging, or damage. Clean dust on electrical components. Measure the insulation performance monthly.
Overload: When the overload protection is triggered, stop the machine. Remove foreign objects and control the feeding amount. Restart after troubleshooting.
Abnormal Noise: Stop the machine immediately if there's abnormal noise. Check for loose parts, wear, and lubrication issues. Repair or replace faulty parts.
Record the maintenance time, content, replaced parts, and equipment operation status each time for future maintenance and equipment management.
We are present worldwide and always here to help.
Get in touch today!