Configuration and Installation of Stone Production Line

Release Date:2016-11-28 Click times:51 Edited by:admin
Consultation Inquiry Hotline: 0086-18336065555
Abstract:We should carry out configuration design and equipment installation as required so as to ensure smooth production in the later stage.
      After purchasing the whole set of equipment for the stone production line, we should carry out configuration design and equipment installation as required so as to ensure smooth production in the later stage.
      Capital construction shall be completed before installation of machine. Check whether the size of abutment is in line with machine size, whether the size and depth of basic hole is correct. Timely clean up the sundries so as to avoid performance degradation of related spare parts.
      Clean the dust and ash stains on the spare parts before installation; apply protective varnish so as to reduce machinery rusting; add lubricate before operation of equipment so as to greatly improve the efficiency of stone production line.
Production Site of Stone Production Line
      After the crushing equipment is transported to the production site, firstly place the foundation bolt in the basic hole through hoisting method, then hang up and place the lower case in the base for installation, finally fasten each bolt to connect it with upper case. Welding will also be applied for tightening if necessary.
     The correct order to install vibrating screen is as follows: motor, v-belt, fixed screening surface and screen box. The whole set of equipment for stone production line shall be installed by professional technician so as to guarantee steady operation of stone production line.
 

 